5
Active projects
₹35.7 Cr / ₹72.3 Cr
Portfolio budget vs spent
2
Blocked tasks
3
Overdue payables
AI daily brief
ClaudeSchedule
Schedule summary:• Skyline Residency — Tower B is 8 pts behind plan (58% vs 66% planned).• Kharadi Villas — Phase 1 is 13 pts behind plan (72% vs 85% planned).
Cost
Cost-overrun watch, as of today:• Kharadi Villas — Phase 1 — 85% of budget spent for 72% progress (+13 pts). Spent ₹8.13 Cr of ₹9.60 Cr.Main driver on Kharadi Villas: waterproofing rework and plumbing running bills. I suggest freezing non-critical POs there until the PMC review on 24 Nov.
Projects
Site locations — Pune
Loading map…
Budget vs actual spend
Skyline Residency — Tower B61%
Hinjewadi Tech Park — Block C38%
Kharadi Villas — Phase 185%
Wakad Commercial Plaza22%
Pimpri Warehouse Shed83%