Overview

Rohan Mehta

5

Active projects

₹35.7 Cr / ₹72.3 Cr

Portfolio budget vs spent

2

Blocked tasks

3

Overdue payables

AI daily brief

Claude

Schedule

Schedule summary:• Skyline Residency — Tower B is 8 pts behind plan (58% vs 66% planned).• Kharadi Villas — Phase 1 is 13 pts behind plan (72% vs 85% planned).

Cost

Cost-overrun watch, as of today:• Kharadi Villas — Phase 1 — 85% of budget spent for 72% progress (+13 pts). Spent ₹8.13 Cr of ₹9.60 Cr.Main driver on Kharadi Villas: waterproofing rework and plumbing running bills. I suggest freezing non-critical POs there until the PMC review on 24 Nov.

Projects

Site locations — Pune

Loading map…

Budget vs actual spend

Skyline Residency — Tower B61%
Hinjewadi Tech Park — Block C38%
Kharadi Villas — Phase 185%
Wakad Commercial Plaza22%
Pimpri Warehouse Shed83%

Need site-level detail? Switch to the Site engineer or Accounts & purchase view.